NE England Shipyard Completes Cableship Conversion Work

Maritime Activity Reports, Inc.

August 1, 2012

'Cable Enterprise': Photo credit Global Marine

'Cable Enterprise': Photo credit Global Marine

Global Marine Systems Energy contracted A&P North East to ready 'Cable Enterprise' for offshore wind farm operations.

The project took 110 days work to make the vessel ready for a contract on the Gwynt y Mor offshore wind farm, situated off the coast of Wales.

Works carried out by A&P North East on the project included; fitting of a carousel to the main deck and under deck stiffening along with  fabrication and installation of a number of items including a forward cow catcher, bulwalk sections, A-Frame seats and plough carriage.

General Manager Ian Douglas commented, “The work scope was completed on time & on budget for Global Marine, We also carried out work assistance to erect & install the carousel.

The complete work package was initially layed out on a general arrangement with changes to the arrangement emerging as the project progressed with class approvals & client requirements.”
 

With the advent of fuel transition, digitalization, AI and autonomy, innovation in vessel design and operation proceeds at unprecedented speed.
Read the Magazine

SERF’s UP

From Data to Decisions: METIS Seeks the Intelligence Behind the Numbers

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week